Status of construction of Permanent Building. 65% work completed as on 07/08/2024 Out of total budgeted cost of Rs. 19.76 Crores, Rs. 18.20 Crores is already disbursed to CPWD Madhopur. The date of commencement of work is 19.11.2022. The Stipulated Date of completion of work is 18.11.2024 and Target Date of Completion of entire scope of work is 30/04/2025.